A budget only tells you something useful when you compare what you planned to spend against what you have actually committed.

How to Track a Project Budget and Manage Cost Changes

Project Budgets
Enquire Now

How to Track a Project Budget and Manage Cost Changes

The four figures that actually matter, a complete worked tracker, and a cost increase taken from discovery through to a recorded decision.

Quick answer

Tracking a project budget means comparing the approved amount against what you have actually spent, what you are committed to but not yet invoiced for, and what you still expect to spend. Those three added together give the forecast final cost, and that is the figure to compare with the budget. Identify differences early, work out what caused them, and take options to whoever holds the authority rather than absorbing the change quietly.

BSB40920 Certificate IV in Project Management Practice

Delivered by Vanguard Business Education (RTO 91219)

  • Price: $1,970 AUD course fee, paid as 2 monthly payments of $985, or from $85 a fortnight on a payment plan (plans total $1,970 to $2,210)
  • Payment plans: 2 monthly payments of $985 ($1,970 total), 3 monthly payments of $684 ($2,052 total), 6 monthly payments of $358 ($2,148 total), or 26 fortnightly payments of $85 ($2,210 total)
  • Duration: self-paced, up to 12 months to complete
  • Delivery: 100% online, self-paced, with qualified trainer support
  • Included: qualified trainer support, all learning resources, assessments and SmartCoach™ learning assistance
  • Entry requirements: no formal entry requirements
  • RPL available: yes, Recognition of Prior Learning and credit transfer may apply
  • Nationally recognised: yes, AQF Level 4

Enrol or find out more about the BSB40920 Certificate IV in Project Management Practice

Key takeaways

  • Spend to date tells you almost nothing. Forecast final cost is the number that matters.
  • Keep actuals, commitments and remaining estimates in separate columns, or you will double count.
  • Keep the original approved budget visible when it changes. Rewriting it hides what happened.
  • A proposal is not an approval. Nothing moves into the approved column until someone with authority says so.
  • Not every overspend is poor management. Some are price rises nobody controlled.

What should a simple project budget include?

Whatever the project will actually cost, grouped so that a difference in one area is visible rather than buried. Common categories:

  • Staff time, where it is costed. Many small projects do not cost internal time, which is a choice rather than an oversight, but be consistent about it.
  • Suppliers and contractors
  • Equipment, purchased or hired
  • Software and licences
  • Other project expenses: printing, venue, travel, consumables
  • Contingency, an agreed allowance for the things you cannot foresee

The right categories depend on the project. A system implementation and an office move have very little in common on this list. What matters is that each category is something you could ask a sensible question about.

Set an agreed budget before tracking expenditure

Record three things when the budget is approved, and keep them where you can find them later.

The approved amounts, by category. This becomes your baseline and it does not change unless someone with authority changes it.

The assumptions behind them. Thirty attendees at $30 a head. Two days of contractor time at the quoted rate. Assumptions are what you check first when a figure moves, and they are impossible to reconstruct six weeks later.

Who can approve changes, and up to what amount. A named person, not a role nobody can find.

When the budget does change, record the change alongside the original rather than overwriting it. A budget that silently becomes whatever was spent teaches nobody anything.

Understand the figures you are tracking

FigureWhat it meansWhere it comes from
Approved budgetWhat was agreed, plus any approved changesThe approval record
Actual expenditureMoney spent and invoicedAccounts or invoice records
Committed costsOrders placed or agreements made, not yet invoicedPurchase orders, confirmed bookings, signed quotes
Further estimated costsWork still to come that has not yet been orderedYour own estimate from the remaining plan
Forecast final costActual + committed + further estimatedCalculated
The double counting trap. When a supplier invoice arrives for something you had recorded as committed, move it, do not add it. The amount leaves the committed column and enters actuals. Leaving it in both is the single most common error in simple budget trackers, and it quietly inflates the forecast.

Build a simple budget tracker

Illustrative example

The same fictional project used in our planning guide: a four-partner accounting firm running a one hour information session for small business clients. Position shown at Day 19, once attendee numbers were confirmed at 28. All figures exclude GST.

Budget trackerIllustrative example: client information session, Day 19, excluding GST
Cost itemApproved budgetActual to dateOutstanding commitmentsFurther estimatedForecast finalVariance
Venue hire$600$600$0$0$600$0
Catering$900$0$980$0$980+$80
Printed handouts$250$0$0$230$230−$20
AV equipment hire$200$200$0$0$200$0
Contingency$150$0$0$0$0−$150
Total$2,100$800$980$230$2,010−$90

Forecast final cost = actual + outstanding commitments + further estimated. Variance = forecast final cost minus approved budget, so a positive figure means forecast spending exceeds the approved budget. The practice manager updates the tracker weekly from the accounts system and the booking confirmations.

Compare expected final costs with the budget

Look at that tracker as a partner might. Spend to date is $800 against an approved $2,100. Barely a third of the budget gone. Comfortable.

It is not comfortable, and it is not a meaningful comparison. Nothing has been invoiced for catering yet, and catering is nearly half the project. The forecast final cost of $2,010 is the honest figure, and it is only below budget because the $150 contingency has not been touched.

This is why spend to date is close to useless on its own. A project can be 20 per cent spent and 90 per cent committed, and a project can look dangerously overspent in month one simply because an annual licence was paid upfront. Always compare the forecast with the budget.

Investigate a cost difference

Catering shows +$80. Before telling anyone the project is over on catering, work out why.

  1. Establish the cause. The budget assumed 30 attendees at $30 a head. The caterer’s current rate is $35, and 28 confirmed attendees gives $980. The rate rose; the numbers fell slightly.
  2. Check the remaining work. Catering is now fully committed, so this figure will not move again unless numbers change.
  3. Work out the effect on the whole project. At project level the forecast is still $90 under budget, because the contingency is intact.

That third step is what turns a figure into useful information. “Catering is over by $80” invites a reaction. “Catering is over by $80 because the rate rose, and the project is still $90 under overall” invites a decision, or no decision at all, which is often the right outcome.

Worth saying plainly: a supplier raising prices is not evidence of poor management. Treating every variance as a failure is how people learn to stop reporting them.

Assess a proposed change

At Day 20 the managing partner asks whether attendees could be given a printed folder with the firm’s service summary alongside the handout. Quoted at $170.

Assess it on four dimensions together, because changing one moves the others.

DimensionEffect
Cost$170. Forecast would move from $2,010 to $2,180, which is $80 above the approved budget
ScopeAn addition. Folders were not in the original scope
TimingPrinting is already scheduled for Days 20 to 21. Adding folders is feasible only if ordered today
QualityNo effect on the session itself. Arguably improves the follow-up

Then put options rather than a yes or a no.

A. Keep the original scope

No folders. Project finishes around $90 under budget. Nothing is lost that was ever promised.

B. Substitute

Upgrade the existing handout to include the service summary instead, for roughly $60 more. Within contingency, no budget change needed.

C. Add the folders and increase the budget

The $150 contingency covers most of the $170, leaving $20 short, so the budget needs to rise by $80 to hold the variance at zero. Requires approval.

Note what has not happened. The forecast is still $2,010. A proposal is not an approval, and nothing enters the approved budget column until the decision is made and recorded. Letting an unapproved request quietly become the new baseline is how budgets stop meaning anything.

Record approval and update the forecast

The managing partner chooses option C. Here is the record.

Change recordIllustrative example: CR-01
Change
Add 30 printed client folders to accompany the handout
Requested by
Managing partner, Day 20
Cost
$170 excluding GST
Effect
Forecast final cost rises from $2,010 to $2,180. Contingency of $150 absorbs most of it, leaving $80 above the approved budget of $2,100
Options put
Keep original scope; substitute an upgraded handout at about $60; add folders and increase the budget by $80
Decision
Approved. Folders added and the approved budget increased by $80 to $2,180. Original budget of $2,100 retained on the record
Approved by
Managing partner, Day 20
Tracker updated
Printing category: approved $330, further estimated $400, forecast $400. Project forecast $2,180 against approved $2,180, variance $0

One distinction worth holding onto. The practice manager costed the change, worked out its effect and prepared the options. The partner approved the money. Preparing a decision and holding the authority to make it are different jobs, and a project support role does the first, not the second.

Communicate the position clearly

A budget update is three sentences, not a spreadsheet attachment nobody opens.

Budget update, Day 20. Forecast final cost is $2,180 against an approved budget of $2,180, so the project is on budget. Catering came in $80 above the original allowance because the caterer’s per-head rate rose from $30 to $35, and the client folders approved today added $170, of which $150 came from contingency and $80 was approved as a budget increase. No further decisions needed before the session.

State the position, the reason for any difference and what decision is required. If no decision is required, say that too, because silence reads as a problem being hidden.

Close out the budget

When the work finishes, the budget is not finished. Three things remain.

Chase outstanding invoices. Anything still in the committed column needs to arrive and be paid, or be released if it was never going to be charged.

Reconcile. Check your tracker against the accounts records. They should agree. Where they do not, find out why before you close, not after.

Capture what you learned about estimating. The catering rate had risen since the last event and nobody checked. That is worth a line in the review note, because the next estimate will be better for it. Lessons that stay in someone’s head are not lessons.

For the wider planning method this budget sits inside, see our guide to writing a simple project plan and schedule, which uses the same example project.

Frequently asked questions

How do you track a project budget?

Record the approved budget, then track three separate figures against it: what has actually been spent, what you are committed to but have not yet been invoiced for, and what you still expect to spend. Adding those three gives your forecast final cost, which is the number you compare with the approved budget.

What is the difference between actual costs and committed costs?

An actual cost is money already spent and invoiced. A committed cost is an order you have placed or an agreement you have made where the invoice has not arrived. Both count towards the final figure, and counting the same order in both columns is the most common tracking error.

Does spending less than the budget mean a project is on track?

No. Expenditure to date tells you nothing on its own, because work still to come carries cost still to come. A project that has spent a third of its budget with three quarters of the work remaining is heading over. Compare the forecast final cost with the approved budget, not the spend to date.

What should you do when a project cost increases?

Establish the cause and the effect on the final figure before proposing anything. Then present options: keep the original scope and absorb the increase if there is room, substitute something cheaper, reduce scope, or request additional funding. Take the options to whoever holds the authority and record their decision.

Who approves a project budget increase?

Whoever holds the financial authority, which is named when the budget is approved. Preparing the information for that decision and holding the authority to make it are different roles. A support role can recommend, cost and document a change, but the approval has to come from the person with the delegation.

Practise this on a full project

Cost planning, tracking and change control are part of the practical work in the Certificate IV, assessed on documents you produce rather than questions you answer.

Ask About the Course

See the units and assessments on the BSB40920 Certificate IV in Project Management Practice course page.

CT

About the author. Cliff Turner is the founder and CEO of Vanguard Business Education (RTO 91219). He designs the project planning, scheduling and risk tasks learners complete in its project management qualifications, built around the way small and mid-sized Australian businesses actually run projects. Connect with Cliff on LinkedIn.

Vanguard Business Education – RTO 91219 · BSB40920 Certificate IV in Project Management Practice · Delivered 100% online across Australia

Leave a Reply