You are currently viewing How to Create a Project Risk Register: A Practical Example
A risk register is only useful if it names who is watching each risk and what they will do when it happens.

How to Create a Project Risk Register: A Practical Example

Project Risk Register
Enquire Now

How to Create a Project Risk Register: A Practical Example

Seven steps to a register people actually use, a complete worked example, and one risk followed from identification through to escalation.

Quick answer

A project risk register records things that might go wrong, what would happen if they did, what is already in place to prevent or limit them, what further action is planned, and who is watching each one. It is a working document rather than a planning formality, which means it has to be reviewed as the project changes. A register written once and never reopened does nothing at all.

BSB40920 Certificate IV in Project Management Practice

Delivered by Vanguard Business Education (RTO 91219)

  • Price: $1,970 AUD course fee, paid as 2 monthly payments of $985, or from $85 a fortnight on a payment plan (plans total $1,970 to $2,210)
  • Payment plans: 2 monthly payments of $985 ($1,970 total), 3 monthly payments of $684 ($2,052 total), 6 monthly payments of $358 ($2,148 total), or 26 fortnightly payments of $85 ($2,210 total)
  • Duration: self-paced, up to 12 months to complete
  • Delivery: 100% online, self-paced, with qualified trainer support
  • Included: qualified trainer support, all learning resources, assessments and SmartCoach™ learning assistance
  • Entry requirements: no formal entry requirements
  • RPL available: yes, Recognition of Prior Learning and credit transfer may apply
  • Nationally recognised: yes, AQF Level 4

Enrol or find out more about the BSB40920 Certificate IV in Project Management Practice

Key takeaways

  • A risk might happen. An issue already has. They need different responses.
  • Vague entries cannot be acted on. Write the cause, the event and the effect.
  • Rate against the controls you already have, and label any post-action rating as anticipated.
  • Every risk needs one named owner. “The team” is not an owner.
  • A trigger turns a register from a list into something that tells you when to act.

What is a project risk register?

A single list of the things that could affect your project, with enough detail attached that someone could act on each one.

Its practical purpose is not to prove you thought about risk. It is to make uncertainty visible early enough to do something cheap about it, rather than something expensive about it later. Spotting in week one that your only trained operator takes leave in week six costs a conversation. Spotting it in week six costs the schedule.

For a small project this is five or six lines you look at weekly. It does not need software, a methodology or a committee.

What is the difference between a risk and an issue?

A risk might happen. An issue already has.

RiskIssue
The supplier might miss the delivery dateThe supplier has confirmed a two week delay
Attendance might fall short of the targetRSVPs closed at 14 against a target of 25

The distinction matters because the response differs. A risk is managed: you reduce its likelihood, limit its consequence, or decide to accept it and watch. An issue is resolved, usually by someone with more authority and usually with less time available.

When a risk occurs it becomes an issue. Note that in the register, so the record shows what was foreseen and what happened, rather than quietly deleting the line.

The seven steps

Step 1: Identify risks against the plan

Work through the project plan rather than brainstorming in the abstract. Go along the tasks, the dependencies, the people, the suppliers, the costs and the assumptions, asking what would have to go wrong for each one to fail.

Assumptions are the richest source. Every assumption is a risk that has not been written down yet. Involve the people doing the work, because they know where it breaks.

Step 2: Write a specific risk statement

Three parts: the cause, the uncertain event and the potential effect.

Not useful: “Staff problems.”
Useful: “Because two of six staff are rostered on client work during the training week, they may miss training, which would delay go-live.”

The second version tells you who to talk to and what to do. The first tells you nothing, and a register full of first versions is why registers get abandoned.

Step 3: Assess likelihood and consequence

Use whatever scale your organisation has agreed. If there isn’t one, a simple three point scale is enough for a small project, provided you write down what each level means. Consistency across entries matters far more than how sophisticated the scale is.

Step 4: Record existing controls and further responses

Separate what is already in place from what is still proposed. A control that exists today reduces your exposure now. A control someone intends to implement next month does not, and conflating the two is how registers end up describing a project that is safer than the real one.

A response either reduces the likelihood of the event, or limits the consequence if it happens. Knowing which one you are attempting is useful.

Step 5: Assign ownership and dates

One named person per risk, responsible for watching it. If an action is planned, name who is doing it and by when. Risks owned by “everyone” are watched by no one.

Step 6: Identify triggers and escalation points

A trigger is the observable thing that tells you to act. “RSVPs below 20 by Day 15” is a trigger. “Keep an eye on attendance” is not.

Decide in advance what would need a decision from someone more senior, and say so. That way the escalation happens because a threshold was crossed, not because someone finally panicked.

Step 7: Review and update

Set a review rhythm and keep it. At each review: close risks that have passed, update ratings where controls have been implemented and shown to work, add new risks the project has created, and move anything that has occurred into issues.

Worked example: a small customer event

Illustrative example

The same fictional project used in our planning and budget guides: a four-partner accounting firm running a one hour information session for around 40 invited small business clients. Register as at Day 8, just after invitations were sent.

The scale used here. Illustrative only, not a standard. Likelihood: Low, unlikely in this project; Medium, could reasonably happen; High, more likely than not. Consequence: Low, absorbed without changing the plan; Medium, the plan or budget moves; High, the session cannot go ahead as intended. Priority combines the two. Ratings reflect the controls already in place.
Risk register, part 1: assessmentIllustrative example: client information session, Day 8
IDCause, event and consequenceLikelihoodConsequencePriority
R1Because the venue holds provisional bookings, the room may be released before final confirmation, meaning the session would need rescheduling and invitations reissuingLowHighMedium
R2Because the caterer is being booked at short notice, they may be unable to confirm final numbers in time, meaning catering would need to be arranged elsewhere at higher costMediumMediumMedium
R3Because the topic is narrow and clients are busy at this time of year, attendance may fall below 25, meaning the session’s purpose would not be metMediumHighHigh
R4Because the AV equipment is hired and untested in the venue, it may fail on the day, meaning the presentation could not be shown as plannedLowMediumLow
R5Because only one person is preparing and delivering the content, illness or a client emergency may make them unavailable, meaning the session would be postponedLowHighMedium
Risk register, part 2: response and ownershipSame risk IDs
IDExisting controlsFurther actionOwnerTrigger or review date
R1Written booking confirmation received Day 3Reconfirm with venue one week before the sessionPractice managerDay 15
R2Caterer has provided a written quote and holds the dateIdentify one alternative caterer who could cover 30 at short noticePractice managerTrigger: caterer has not confirmed by Day 19
R3Invitations sent to 40 clients Day 8, with a response dateSend a reminder to non-responders; prepare a second invitation list if neededPractice managerTrigger: fewer than 20 RSVPs by Day 15
R4Hire includes same-day replacementTest equipment in the venue during the rehearsal; bring printed slides as backupSenior accountantDay 12, at rehearsal
R5Content and slides stored centrally, not on one laptopBrief a second partner well enough to deliver the session if requiredManaging partnerDay 18

Ratings reflect the existing controls only. Where a further action would change a rating, that rating is anticipated until the action has been implemented and reviewed.

One risk, from identification to escalation

Follow R3, low attendance, because it shows what a register is for.

Day 8Identified and rated. Likelihood Medium, consequence High, priority High. Trigger set at fewer than 20 RSVPs by Day 15
Day 12Response implemented. Reminder sent to the 26 clients who had not responded
Day 15Review. RSVPs at 14. The trigger has been crossed
Day 16Escalation. Decision taken to invite a second client segment

At the Day 15 review the practice manager does not simply note that numbers are low. The trigger was set in advance, it has been crossed, and that was agreed to mean a decision is needed rather than more waiting. The register says who makes it.

The managing partner decides to extend invitations to 20 clients in an adjacent segment, accepting that RSVPs will now close later and that catering numbers will be confirmed closer to the date. R3 stays open with its likelihood revised, and a new risk is added covering the compressed catering timeline. By Day 19 attendance has reached 28.

What made that work. Not the register itself. The trigger. Without “fewer than 20 by Day 15”, the Day 15 conversation is somebody saying numbers feel a bit light and everyone agreeing to see how it goes. The trigger converted a vague worry into a decision point.

Common mistakes to avoid

  • Vague descriptions. “Supplier issues”, “staff availability”, “budget”. Nobody can act on a category.
  • Inconsistent ratings. Rating one risk against existing controls and the next against hoped-for ones makes the priorities meaningless.
  • Missing owners. Every risk needs one name. Not two, not a team.
  • Proposed controls treated as done. The most dangerous of the five, because the register then describes a project safer than the one you have.
  • Never reviewed. Written during planning to satisfy a requirement, never opened again. Exposure changes as the project moves.
  • Too many entries. Thirty risks is a document. Six is a tool. Record what could genuinely affect the project.

Create your first register

Use the structure from the worked example: ID, cause and event and consequence, likelihood, consequence, priority, existing controls, further action, owner, trigger or review date. Two tables if it is easier to read, sharing the same IDs.

  1. Open your project plan and go through the tasks, dependencies, suppliers, people, costs and assumptions.
  2. Write five or six risks as cause, event and effect. Resist the urge to list twenty.
  3. Define your likelihood and consequence levels in writing before you rate anything.
  4. Rate each risk against the controls that exist today.
  5. Add further actions where a risk warrants it, with a name and a date.
  6. Set a trigger for anything you would otherwise just worry about.
  7. Put a weekly review in the calendar and keep it.

A register does not remove risk. Things will still go wrong on a project with a good register. What changes is that you find out earlier, you have already decided what to do, and someone has already agreed who decides.

This sits alongside the project plan and schedule and the budget tracker for the same example project.

Frequently asked questions

What is a project risk register?

A risk register records uncertain events that could affect a project, what would happen if they occurred, what is already in place to prevent or limit them, what further action is planned, and who is watching each one. Its purpose is to support decisions during the project, which means it only works if it is reviewed.

What is the difference between a risk and an issue?

A risk might happen. An issue already has. The supplier might miss the delivery date is a risk; the supplier has confirmed a two week delay is an issue. When a risk occurs it becomes an issue and moves out of planning and into action, which is a different response and often a different person.

How do you write a good risk statement?

Include the cause, the uncertain event and the potential effect. Staff problems is not a risk statement because nobody can act on it. Two of six staff are rostered on client work during the training week, so they may miss training, which would delay go-live is something you can do something about.

How do you rate project risks?

Use whatever scale your organisation has agreed, applied consistently. If you have none, a simple three point scale for likelihood and consequence is enough for a small project, provided you define what each level means in writing. Consistency between entries matters more than the sophistication of the scale.

How often should a risk register be reviewed?

At a regular rhythm matched to the project, and whenever something significant changes. For a short project a weekly look is usually right. A register written once and never reopened is the most common failure, because exposure changes as the work progresses and completed actions should change the ratings.

Practise this on a full project

Risk identification, assessment and treatment are part of the practical work in the Certificate IV, assessed on a register you build and defend rather than questions you answer.

Ask About the Course

See the units and assessments on the BSB40920 Certificate IV in Project Management Practice course page.

CT

About the author. Cliff Turner is the founder and CEO of Vanguard Business Education (RTO 91219). He designs the project planning, scheduling and risk tasks learners complete in its project management qualifications, built around the way small and mid-sized Australian businesses actually run projects. Connect with Cliff on LinkedIn.

Vanguard Business Education – RTO 91219 · BSB40920 Certificate IV in Project Management Practice · Delivered 100% online across Australia